Restaurant Construction

Restaurant Renovation & Build-Out Contractor in Toronto & GTA

Full-service restaurant construction and renovation across Toronto and the Greater Toronto Area — from permits to final inspection.

Get a Free Estimate
Completed restaurant dining room built by Buildup Contracting in the Greater Toronto Area

Full Restaurant Build-Out

From base building condition to fully operational restaurant space, including:

  • Interior framing & finishing
  • Commercial kitchen construction
  • HVAC coordination
  • Fire suppression & code compliance
  • Electrical & plumbing integration

Plaza Restaurant Renovation

Efficient renovation solutions for existing plaza and retail units.

We understand landlord requirements, utility upgrades, and tight opening timelines.

Commercial Kitchen Expertise

Restaurant construction requires precision in:

  • Make-up air systems
  • Exhaust & grease duct systems
  • Fire suppression coordination
  • Health & safety inspection standards

Our subcontractor teams are experienced in these specialized requirements.

Permit Coordination Support

We coordinate with the architect and engineering consultants on your project to optimize permit drawings based on real construction experience — reducing costly revisions during inspections.

Why Toronto Restaurant Owners Choose Buildup Contracting

A restaurant answers to more inspectors than any other commercial interior — building, health, fire, TSSA — and usually on a lease clock that started months ago. We build restaurants for a living, so we know what each department looks for, and which approval quietly breaks an opening date when nobody starts it early enough.

Wondering about budget first? Our 2026 restaurant build-out cost guide breaks down real per-square-foot ranges by concept.

Opening a franchise location? See our franchise & multi-unit construction page — brand-standard packages, franchisor coordination, and opening-date schedules.

Commercial kitchen with stainless steel cook line and exhaust hood, restaurant build-out in the GTA

Restaurant-Specific Experience

Unlike general contractors who dabble in food service, our entire team understands the unique demands of commercial kitchen construction — from Type I hood installations and Ansul systems to grease trap placement and three-compartment sink rough-ins. We’ve completed dozens of restaurant build-outs across Toronto, Mississauga, Vaughan, Markham, and Richmond Hill.

Permit Expertise That Saves Weeks

We coordinate with your architect on permit-ready drawings informed by real construction experience, reducing revision cycles with municipal building departments. Building permit, plumbing permit, TSSA on the gas line — we run the whole submission and inspection sequence while you hire and train your staff. Gas work is handled by registered/certified fuels contractors.

On-Time, On-Budget Delivery

Every week of construction delay costs you revenue. We provide detailed project schedules with milestone tracking and coordinate all trades in sequence — and if a date moves, you hear it from us first, with the reason. Our typical restaurant build-out in the GTA takes 8–16 weeks from permit approval to occupancy, depending on scope and complexity.

Team experience includes franchise & food-service brands:

Popeyes wordmark - team franchise project experience

Recent restaurant projects

Real Toronto & GTA Restaurant Build-Outs

Built by our own crew and photographed on site — with the actual size, schedule and budget for each.

Toronto approvals

The Toronto Approvals That Set Your Opening Date

Toronto is not the 905. A restaurant here answers to several departments running on separate clocks, and the one that breaks an opening date is usually not the building permit — it is the sign permit or the public health walk that nobody started early enough.

ApprovalWho reviews itWhen to start
Building permitToronto BuildingAt drawing sign-off — it gates demolition
Kitchen plan review & pre-opening walkToronto Public HealthBook the walk three weeks before your target opening
Hood, suppression, exitsToronto Fire ServicesPre-opening fire walk, once equipment is set
Storefront signCity sign permit teamAt lease signing — it runs a 4–10 week clock of its own
Gas connectionsTSSAWith the mechanical package
Zoning & Eating or Drinking Establishment licenceMunicipal Licensing & StandardsBefore you commit to the space
PatioCafeTOSpring window — miss it and you wait a season
Liquor licenceAGCOIn parallel with construction

Budget

What a Restaurant Build-Out Costs in Toronto

In 2026 GTA dollars, most quick-service refreshes come in at $70–120 per square foot turnkey, and full-service casual restaurants typically run $180–300 per square foot. Fine-dining and heavy-ventilation concepts go higher.

The spread inside those bands has almost nothing to do with finishes. The same concept can land near $300/sf in a former restaurant that already has a working hood and a correctly sized grease interceptor, and cost far more in a bare retail shell where exhaust, make-up air, the gas line and under-slab drainage all have to be built from nothing. That is the first thing we check on a site walk, and it is the single biggest number in your budget.

ConceptTypical 2026 GTA rangeWhat decides where you land
Quick-service refresh, turnkey$70–120 / sfWhether the hood, grease interceptor and gas line can be re-used as-is
Full-service casual, turnkey$180–300 / sfSize of the cook line, seat count, and how many washrooms the code requires
Fine dining and heavy-ventilation conceptsAbove that band — quoted per projectPer-table exhaust, make-up air tempering, and the electrical service it needs

Scope

What Is Actually in a Restaurant Build-Out

A restaurant is not a retail fit-out with a kitchen bolted on. Eight trades have to land in the right order, and the ones nobody sees after opening day are the ones that decide whether you pass inspection on the first walk. This is the scope we price, build and sign off on every restaurant project.

TradeWhat we buildWhat goes wrong when it is not coordinated
Demolition and structureStrip-out, floor saw-cutting, new partitions and bulkheads, and structural openings where a hood, walk-in or new washroom needs them.Under-slab conditions discovered after finishes are ordered, which stops the whole schedule instead of one trade.
Plumbing and drainageSanitary and vent runs, floor and trench drains, a grease interceptor sized to your fixture load, and hot water capacity for the dish area.An interceptor sized off the previous tenant's menu rather than yours — usually caught at the health inspection, not before it.
Exhaust and make-up airType I or Type II hood, ductwork to the roof, fans and curbs, and tempered make-up air balanced against the exhaust volume.A kitchen that pulls the front door shut and pushes fryer smell into the dining room because make-up air was value-engineered out.
Electrical and low voltageService upgrade where the panel cannot carry the kitchen, dedicated equipment circuits, emergency and exit lighting, and POS and data rough-in.Equipment delivered before anyone confirmed the incoming service could carry it, turning a two-day fix into a utility timeline.
Fire suppression and life safetyWet chemical suppression over the cook line, extinguishers, alarm tie-ins, and exit and egress work to code.Suppression scheduled after equipment is set, which forces a second mobilization and pushes the pre-opening fire walk back a week.
Finishes and millworkWashable wall and ceiling assemblies, commercial flooring with proper coving, front counter, banquettes, shelving and service millwork.Finishes chosen to photograph well rather than to pass a health inspector's cleanability test, then replaced at your cost.
Equipment set and connectionsReceiving, setting, levelling and connecting owner-supplied and supplied equipment, walk-in assembly, and gas connections through TSSA.Equipment arriving at a site that is not ready to receive it, then sitting in storage on your invoice.
Inspections and handoverBuilding, fire, health, electrical and TSSA sign-offs sequenced in the right order, deficiency walk, and manuals handed over at the end.Inspections booked out of sequence, so occupancy waits on a walk that could have happened two weeks earlier.

All of it sits on one contract with one schedule and one person to call. You are not managing a plumber, a hood installer and a millworker who each blame the other for the same two-week delay.

Schedule

What the 8 to 16 Weeks Actually Look Like

Construction is the part everyone counts, but it is rarely the part that moves your opening date. Permit review and long-lead equipment run on clocks we do not control, so we start both on day one and build the schedule backward from the date you want to open.

StageTypical durationWhat is happening
Site walk to written scope1 business dayWe walk the unit, read the lease and the work letter, and send a scope with a first read on budget.
Drawings and permit submission2 to 5 weeksArchitectural, mechanical and kitchen drawings coordinated, then filed. Long-lead equipment is ordered in this window, not after.
Permit reviewVaries by municipalityRuns in parallel with equipment lead times. Review speed differs city to city across the GTA — we compare them in our permit timeline guide.
Demolition and rough-in2 to 4 weeksStrip-out, saw-cutting and under-slab drainage, framing, and the plumbing and electrical rough-in that the first inspections cover.
Mechanical, exhaust and suppression2 to 3 weeksHood and ductwork set, roof fans and curbs, make-up air balanced to the exhaust, wet chemical suppression over the line.
Finishes and millwork2 to 4 weeksWashable wall and ceiling assemblies, commercial flooring and coving, front counter, banquettes and service millwork.
Equipment set and connections1 to 2 weeksReceiving, setting and connecting the line and refrigeration, walk-in assembly, and gas connections signed off by TSSA.
Inspections, deficiency walk, handover1 to 2 weeksBuilding, fire and health walks booked in the right order, deficiency list closed out, keys and manuals handed over with a one-year workmanship warranty.

The two stages that stall projects are the ones people treat as paperwork: the permit and the sign permit, which runs a four to ten week clock of its own and is often started far too late. Both begin the week we are engaged.

Before you sign

Seven Things We Check Before You Commit to a Space

Most restaurant budgets are decided before construction starts — at the moment the lease is signed. A free site walk takes about forty minutes and answers all seven of these. Bring us in before you sign and the estimate you get is a real number instead of a range.

What we checkWhy it decides your budget
Zoning and use permissionA unit that is not zoned for an eating establishment can cost you months, or the deal. This is the one item worth checking before the offer, not after.
Existing exhaust and roof accessA usable hood, curb and roof path is the single largest saving available to you. Building exhaust from nothing in a bare shell is a five-figure line on its own.
Drainage and the grease interceptorUnder-slab drainage means saw-cutting the floor. An interceptor sized for the previous tenant is often undersized for your menu, and the health inspector is the one who tells you.
Incoming gas and electrical capacityIf the panel or the gas line cannot carry your equipment list, the upgrade is a utility timeline, not a construction timeline — and it will not compress.
Make-up air and HVAC conditionExhaust without tempered make-up air pulls the front door shut and freezes your dining room in January. It has to be sized with the hood, not after it.
Washrooms and barrier-free complianceFixture counts and barrier-free requirements scale with seat count. Adding twenty seats can add a washroom you had not budgeted for.
The landlord work letterWhat the landlord delivers, what they will contribute, and what they will charge back. The gap between the work letter and your scope is real money, and it is negotiable while the lease is not signed.

If you already have the drawings, send them with the unit address and we will come back with a preliminary scope and a first read on budget within one business day.

Restaurant Construction Across the Greater Toronto Area

Buildup Contracting serves restaurant and food service clients throughout the GTA, including Toronto (downtown, midtown, North York, Scarborough, Etobicoke), Mississauga, Brampton, Vaughan, Markham, Richmond Hill, Oakville, and Burlington. A new concept on a downtown corner gets the same crew and the same process as a plaza unit conversion in a suburban strip mall — we don't run an A team and a B team.

Our portfolio includes full-service restaurants, quick-service and fast-casual concepts, bubble tea and café fit-outs, bakery production kitchens, ghost kitchens and commissary spaces, and food court units. The cuisine changes; the inspections don't — and we've built for both.

Stainless service window and illuminated menu boards at a completed gas station restaurant build-out in Vaughan

100+

Commercial build-outs delivered

8 years

Hands-on commercial construction

8–16 weeks

Typical mid-size build-out

1 year

Workmanship warranty on every project

4.9 ★

Average from 17 Google reviews

WSIB & CGL

Insured — certificate on request

Common questions

Restaurant Construction FAQs — Toronto & GTA

How long does a restaurant build-out take in Toronto?

Most mid-size restaurants run 8–16 weeks of construction. A recent Toronto quick-service restaurant went from vacant shell to opening-ready in nine weeks, and a 500 sf café refresh took six. What moves the number is the building permit, long-lead kitchen equipment, and whether the space already has exhaust and drainage.

What does a restaurant build-out cost per square foot?

In 2026 GTA dollars, quick-service refreshes run $70–120 per square foot turnkey and full-service casual restaurants $180–300 per square foot. A former restaurant with a working hood and a correctly sized grease interceptor costs far less to convert than a bare retail shell.

Which approvals do I need in the City of Toronto?

A building permit from Toronto Building, kitchen plan review and a pre-opening walk from Toronto Public Health, a pre-opening fire walk from Toronto Fire Services, a separate storefront sign permit, TSSA sign-off on gas, and zoning plus an Eating or Drinking Establishment licence through Municipal Licensing & Standards. Patios go through CafeTO and liquor through the AGCO.

Do you handle the permit application yourself?

Yes. We coordinate the drawing set with your architect or designer, manage the submission, and sequence inspections so the job does not stall waiting on a sign-off.

Can you build while our business stays open?

Yes. We built a national brand’s take-out kitchen into the back of a Vaughan gas station convenience store that never closed. Phasing, dust and noise control, protection of customer areas and after-hours work windows are part of the normal plan.

Do you work outside the City of Toronto?

Yes, across the GTA. Our office is in Richmond Hill and our crews work through Toronto, York Region and Peel — including Mississauga, Vaughan, Markham and Brampton.

Are you insured?

Yes. We carry WSIB coverage and commercial general liability, with a certificate of insurance available on request for your landlord or franchisor.

What do I get after a site walk?

A written scope of work and an estimate within one business day, plus a schedule sequenced backward from your target opening date. Every project carries a one-year workmanship warranty.

Do I need a general contractor, or can I hire the trades myself?

You can hire trades directly, and on a light cosmetic refresh it sometimes makes sense. On a restaurant it usually does not. The hood, the make-up air, the suppression system, the gas connection and the electrical service all have to be sized against each other and inspected in a fixed order. When each trade holds only their own piece, the sequencing gaps land on you — and so does the cost of a failed inspection. A general contractor carries that risk, the schedule and the warranty on one contract.

What does a landlord work letter usually cover?

It sets out what the landlord delivers with the unit, what they will contribute toward your build, and what they will charge back to you. The gap between that letter and your actual scope is real money — roof penetrations for exhaust, incoming service capacity, demising walls and base building HVAC are the usual arguments. Send us the work letter with the drawings and we will tell you what it does not cover before you sign.

Can you take over a project another contractor started?

Yes, and it is more common than people expect. We start with a condition and compliance review — what has been built, what has been inspected, what has been closed out with the city, and what has been paid for. You get a written scope for the remaining work and a realistic reopening date, not an optimistic one. Where work has to be reopened to pass inspection, we tell you that before you sign, not after.

What happens if an inspector fails something?

We correct it and rebook the inspection, and workmanship deficiencies are on us, not on your budget. The way to avoid it is sequencing: pre-inspection walks before the official one, suppression installed before equipment is set rather than after, and the health and fire walks booked in the order that lets occupancy follow immediately. Every project also carries a one-year workmanship warranty after you open.

★★★★★

4.9 on Google

Every review from a GTA operator we built for

“BuildUp handled the full build-out of our restaurant and I honestly couldn't have asked for a smoother process. Lev understood from day one how important it was to open on schedule, and he kept everything moving — permits, inspections, the kitchen, the dining area — without me having to chase anyone. If you're opening a restaurant and want a contractor who actually takes the stress off your plate, this is the team.”

Kamesh Parcha · via Google

Who you'll actually be dealing with

Lev walks the unit himself and writes the scope you get back — the same person stays on the job through to handover.

A written scope and a first read on budget within one business day of the walk.

Nothing is booked or billed until you say so. The site walk is free anywhere in the GTA.

WSIB clearance · $5M commercial liability · 1-year workmanship warranty · Mon–Fri 8am–6pm

Ready to Build Your Restaurant?

We'll walk your space, review your plans, and put a written scope, timeline and budget in your inbox within one business day.