Dessert Café Refresh — Toronto

By Buildup Contracting

Project featured image

The site

What Made This One Hard

A 500 sf front-of-house refresh has nowhere to hide. Every surface is within arm's reach of a customer, so the wood-slat feature walls, the blacked-out ceiling and the counter finishing all had to be built at a level of detail that a larger room would forgive.

The cafe also had a reopening date already announced. Six weeks was not an estimate to be managed — it was a fixed commitment, which meant lighting, flooring and millwork were ordered before demolition started rather than after the space was opened up.

Project type

Dessert café refresh in an existing streetfront unit.

Location

Toronto, Ontario.

Approximate scope

Compact front-of-house of roughly 500 square feet — service counter with display refrigeration, espresso bar, and dining area — completed for approximately $80,000 in a six-week construction window.

Snowday dessert cafe service counter with display fridge and neon sign after renovation in Toronto
The finished counter on reopening day — display fridge, espresso bar and the Snowday neon over a wood-slat feature wall.

Buildup's role

General contractor on a fast front-of-house refresh, sequenced so the operator could reopen quickly.

Scope of work

  • Wood-slat feature walls and a continuous slat wainscot wrapping the dining room
  • Open ceiling painted out dark, with new track and pot lighting
  • New plank flooring throughout the front-of-house
  • Paint throughout, and finishing around the counter, espresso bar and display equipment
Dining room of a 500 sf Toronto dessert cafe after a six-week renovation
The dining room after the refresh — slat wainscot, blacked-out ceiling and new lighting doing the work in a 500 sf room.

Challenge

Making 500 square feet feel finished rather than cramped: a continuous slat wainscot to wrap the room, a blacked-out ceiling to hide services and add height, and surfaces chosen to take daily winter foot traffic — all sequenced so the operator could reopen quickly.

Timeline

Six-week construction window from start of work to reopening.

Outcome

Reopened on schedule as a warm timber-and-charcoal room — display counter, espresso bar and seating ready for service on day one.

Cafe seating along a wood slat wall in a renovated Toronto dessert shop
Seating along the wood-slat wall — surfaces chosen for daily winter foot traffic.

The result

What the Client Got

A 500 sf front-of-house rebuilt in six weeks for about $80K — wood-slat feature walls, blacked-out ceiling, new lighting and flooring, and the counter finishing that the room is built around.

The cafe reopened on the announced date, with the deficiency walk closed before handover and a one-year workmanship warranty on the work.

★★★★★

4.9 on Google

Every review from a GTA operator we built for

“BuildUp handled the full build-out of our restaurant and I honestly couldn't have asked for a smoother process. Lev understood from day one how important it was to open on schedule, and he kept everything moving — permits, inspections, the kitchen, the dining area — without me having to chase anyone.”

Kamesh Parcha · via Google

Planning something like this?

Lev walks your unit himself and writes the scope you get back — the same person stays on the job through to handover.

A written scope and a first read on budget within one business day of the walk, free anywhere in the GTA.

Nothing is booked or billed until you say so.