← All posts

Restaurant Build-Out Checklist: Lease to Opening Day

Published: April 18, 2026 · Last reviewed: April 2026 · Reviewed by: Buildup Contracting Pre-Construction Team · Service area: Toronto & GTA

This article is for planning purposes only. Cost, timeline, permit, code, gas, grease trap, public health, and accessibility requirements vary by project scope, municipality, landlord, site condition, engineering, equipment list, and current trade and supplier availability. Confirm specific requirements with the municipality, architect, engineer, landlord, public health unit, fire reviewer, AGCO, registered or certified fuels contractor, electrical contractor, or other applicable authorities.

Quick answer

A restaurant build-out moves through eight clear phases, from the first site walk before you sign the lease to the soft-open trial nights before opening day. The owner, the contractor, the architect and engineering team, the landlord, and the city/health/fire authorities each carry specific items inside each phase — and most of the painful surprises in a Toronto or GTA build-out come from items that fell into the gap between those owners. Use the master checklist below on a site walk, during lease review, in design coordination, and through opening week so nothing slides off the table. These are planning checklists that vary by site condition, municipality, supplier availability, and the specific scope your landlord agreed to in the work letter.

If you want to walk this list with a contractor before you sign anything, Buildup Contracting is happy to attend a site visit. We do restaurant build-outs across Toronto and the GTA, including Mississauga, Vaughan, Markham and Richmond Hill.


Why use a master checklist (and how to read this one)

A restaurant build-out is not one project. It is four overlapping projects — a real-estate project (the lease and work letter), a design project (architect, mechanical, electrical, plumbing, kitchen design), a construction project (demo, rough-in, finishes, equipment), and a regulatory project (building permit, health pre-opening, fire, electrical, gas). Each of those four has its own clock, its own owner, and its own failure mode.

The cleanest way to keep them aligned is a phase-by-phase checklist that names who is doing what. That is what this article gives you. Each phase below is presented as a table with these columns:

A check mark in a column means that party is responsible for that item or has to be present for it. More than one check mark in a row is normal — most items are coordination, not solo work. Buildup's role is the construction-side coordination, the on-site reads during a site walk, and the trade scheduling once permits are in. The architect and engineering team own the permit drawings and stamping. The owner owns the menu, the equipment list, the lease decisions, and the opening-day timing.

If you want a parallel cost view alongside this checklist, see our restaurant build-out cost guide. For how the calendar lays out, see the build-out timeline. For the permit side specifically, the Ontario restaurant permits guide walks through every permit family.


Phase 1 — Before signing the lease

This is the cheapest phase to fix problems in. Once the lease is signed, every constraint in the building becomes your problem. Walk the site with a contractor before you sign, not after.

Item Owner Buildup Architect / Engineer Landlord Municipality / Health / Fire
Site walk with contractor before signing Attend Lead Provide access
Read the work letter line by line, including landlord's-work vs. tenant's-work split Lead with Buildup Review Provided document
Confirm electrical panel amperage and available spare capacity Confirm with utility On-site read Confirm in writing
Confirm gas service capacity and meter size Confirm with utility Notes scope Confirm in writing
Identify existing grease interceptor (size, location, age) On-site read Confirm if landlord-owned
Identify existing exhaust shaft / roof penetration paths On-site read Confirm feasibility on plan Confirm rooftop access
Confirm whether the existing space had a previous restaurant use Ask landlord Confirm from drawings Provide history
Confirm zoning permits a restaurant at this address Confirm with municipality Verify on plan Confirm zoning
Confirm parking and accessibility entry requirements for the unit Notes scope Verify on plan Confirm if site plan applies
Confirm fixturing period (free-rent build period) length Negotiate Estimate build duration to support negotiation Negotiate

A few notes on this phase. Mall and plaza landlords sometimes give significant cash tenant-improvement money — we have seen $200,000+ on certain bubble-tea deals — and in other cases the cash is capped and the operator gets free-rent months instead. Both are real planning levers, but TIA outcomes are case-by-case and need to be negotiated against your specific work letter, not assumed. For more on that, see our lease and work letter guide.

The site walk itself usually takes one to two hours. Have your contractor read the panel, look at the ceiling for existing penetrations, look under sinks for existing drains, and look at the back wall for whether a hood path is even possible. None of that is permit work. It is informed feasibility before you commit.


Phase 2 — Before design starts

You have a signed lease and a fixturing period that has started ticking. The next four to eight weeks are design. The faster the owner gives the design team a locked menu and a complete equipment list, the faster the drawings get to permit submission.

Item Owner Buildup Architect / Engineer Landlord Municipality / Health / Fire
Lock the concept and the menu Lead
Provide a complete equipment list (with model numbers, voltages, gas demand) Lead with kitchen designer Review for trade impact Required for drawings
Hire the architect Lead Recommend if needed Engaged
Engage mechanical engineer for hood, exhaust, make-up air Engage via architect Recommend if needed Engaged
Engage electrical engineer for panel and load calculations Engage via architect Recommend if needed Engaged
Engage plumbing engineer for grease, sanitary, hot water Engage via architect Recommend if needed Engaged
Confirm seat count and washroom count target Lead Verify on plan
Provide branding and finishes intent (millwork, tile, lighting direction) Lead Document on plan
Confirm landlord design-review process and timing Confirm Submit for landlord review Review and approve
Confirm signage scope and storefront constraints Confirm with sign vendor Coordinate sign install rough-in Coordinate on plan Approve sign per lease

Equipment lead times drive a lot of this phase. Hoods, walk-ins, and Type-1 hood make-up air units in particular can be eight to fourteen weeks. We track this in our restaurant equipment lead times guide — owners who order long-lead items during design rather than after permit issuance gain weeks back on opening day.

This phase is where Buildup is mostly in advisory mode. Permits are the architect and engineering team's work. Buildup's role here is the constructability read — flagging things on the drawings that will be hard to build, expensive to coordinate, or risky on the inspection day.


Phase 3 — Before permit submission

Drawings are coming together. This phase is about making sure the permit package is complete before it goes in, because resubmissions cost weeks. The City of Toronto's building permit review streams explain how a tenant fit-out is routed.

Item Owner Buildup Architect / Engineer Landlord Municipality / Health / Fire
Final equipment list locked (no more changes) Lead Review for trade impact Confirm on drawings
Architectural drawings stamped Review Stamp and submit Receive submission
Mechanical drawings stamped (hood, exhaust, make-up air, HVAC) Review Stamp and submit Receive submission
Electrical drawings stamped, panel schedule complete Review Stamp and submit Receive submission
Plumbing drawings stamped (grease, sanitary, hot water) Review Stamp and submit Receive submission
Structural review if any new openings, hood curb, or rooftop unit Review Stamp and submit Receive submission
Site plan confirmed (entry, accessibility, parking) Confirm on plan Receive submission
Landlord-side scope confirmed in writing (e.g., who upgrades the panel) Confirm in writing Reference on plan Confirm in writing
Sign permit application started Lead with sign vendor Coordinate on plan Receive submission
Health pre-construction review if required by region Lead Coordinate Receive submission

The owner-confirmed planning-estimate for this phase: building permit review for a typical restaurant tenant fit-out in the GTA is often six to twelve weeks once the package is complete, but timelines vary by municipality and review complexity — see our GTA permit timelines compared for how Toronto, Mississauga, Vaughan, Markham, and Richmond Hill differ.

Buildup's pre-construction permit coordination service runs in parallel with the architect's work in this phase — we are not stamping the drawings, we are reading them for buildability and coordinating with trades so that the day the permit is issued, demo can start.


Phase 4 — Before demo

Permit is issued. Now the construction project takes over from the design project. Demo is the first physical work on site, and it is where surprises (existing structure, existing services, hidden landlord items) surface fast.

Item Owner Buildup Architect / Engineer Landlord Municipality / Health / Fire
Building permit issued Confirm receipt Submission review closed Issue permit
Demo permit pulled (if required separately by municipality) Pull Issue
Construction contract signed and deposit released Sign and fund Sign
Insurance certificates filed with landlord Provide if owner-side Provide builder's risk and liability Receive and file
Hoarding and dust barrier plan in place Lead Approve plan
Site protection (floors, common-area paths, neighbour units) Lead Approve plan
Confirm landlord-side removal scope (e.g., existing landlord-owned mechanical) Confirm Coordinate with landlord trades Confirm and remove
Confirm utilities live, locked out, or capped as needed for demo Coordinate Confirm meter status
Confirm working hours allowed by lease and by municipality noise rules Confirm Schedule trades within window Confirm hours
Pre-demo walkthrough with landlord and contractor Attend Lead Attend

Mall and food-court tenants often have stricter delivery, hoarding, and after-hours rules than street-front plaza tenants. We document those rules in writing during this phase so trades aren't surprised at 7 a.m. on day one.


Phase 5 — Before rough-in

Demo is done, the space is clean, the framing layout is marked. Now the trades come in for rough-in: mechanical ductwork, electrical wiring in walls, plumbing under the slab or in the ceiling, and any structural work for the hood curb or rooftop unit.

Item Owner Buildup Architect / Engineer Landlord Municipality / Health / Fire
Demo complete and inspected on site (note any structural surprises) Lead Address structural finding if any
Mechanical, electrical, plumbing trade scheduling sequenced Lead
Long-lead equipment confirmed in production / shipped Confirm with vendor Track procurement
Hood and make-up air unit ordered, delivery date confirmed Confirm with vendor Procure and stage Verify model matches drawings
Walk-in cooler / freezer ordered, delivery date confirmed Confirm with vendor Procure and stage
Underground plumbing layout reviewed against equipment list Review Confirm on plan
Electrical service upgrade coordinated with utility if required Coordinate with utility Coordinate with electrician Confirm on plan Coordinate access if landlord-owned
Gas service upgrade coordinated with utility / TSSA if required Coordinate with utility Coordinate with gas trade Confirm on plan Coordinate access if landlord-owned TSSA notified
Framing layout marked on slab, walked with owner Walk and approve Lead Confirm on plan
Site safety, first aid, and trade orientation in place Lead

This is where a contractor's trade coordination does the heavy lifting. A restaurant has six to twelve trades on a small footprint. The order they show up in matters as much as the quality of their work.


Phase 6 — Before finishes

Rough-in is complete and inspected. Walls are about to close. This is the moment to confirm everything that goes inside the wall is right, because once drywall is up, it is expensive to revisit.

Item Owner Buildup Architect / Engineer Landlord Municipality / Health / Fire
Plumbing rough-in inspection passed Schedule and host Plumbing inspector attends
Electrical rough-in inspection passed (ESA) Schedule and host ESA inspector attends
Framing / drywall transition inspection (building) Schedule and host Building inspector attends
Hood and make-up air system installed Lead Verify against drawings
Equipment landed and set in place (cooking line, walk-in, prep) Confirm equipment receipt Lead placement
Final electrical connections to equipment scheduled Lead
Final gas connections to equipment scheduled (TSSA) Lead TSSA inspection scheduled
Tile, millwork, finishes ordered and on track Confirm finishes choices Procure and stage Confirm on plan
Washroom rough-in confirmed barrier-free per accessibility requirements Lead Confirm on plan
Storefront and signage scope coordinated Coordinate with sign vendor Coordinate sign rough-in Confirm on plan Approve sign

For specifics on hood and ventilation choices that come up in this phase, see our Type-1 vs Type-2 hood guide. For grease interceptor sizing, see the grease trap sizing guide.


Phase 7 — Before final inspections

Finishes are in. Equipment is connected. The space looks like a restaurant. The next step is a sequence of inspections — building, electrical, gas, plumbing, then health pre-opening, then fire. They have to happen in the right order because some inspectors will not pass until others have.

Item Owner Buildup Architect / Engineer Landlord Municipality / Health / Fire
All trades complete and signed off internally Lead
Inspections scheduled in the right sequence Lead Inspectors attend
Final building inspection passed Schedule and host Address any deficiencies Building inspector attends
Final electrical inspection passed (ESA) Schedule and host ESA inspector attends
Final gas inspection passed (TSSA) Schedule and host TSSA inspector attends
Final plumbing inspection passed Schedule and host Plumbing inspector attends
Hood fire-suppression system installed and tagged Schedule and host Fire inspector reviews
Punchlist underway with owner walk Walk and list Lead and resolve
Operator's documentation pack assembled (manuals, warranties, as-builts) Receive Lead handover Provide as-builts
Health pre-opening application filed with regional public health Lead Coordinate site readiness Public health receives application

The health pre-opening application is the owner's filing, but the readiness of the site is the contractor's responsibility. The City of Toronto's starting a food business guide walks through what Toronto Public Health expects on the day of the pre-opening visit. Region of Peel and York Region public health units have their own equivalents.


Phase 8 — Before opening day

All inspections are passed or in motion. Equipment is calibrated. Staff is being trained. The last week is about removing risk from opening night.

Item Owner Buildup Architect / Engineer Landlord Municipality / Health / Fire
All final inspections passed Coordinate All inspectors signed off
Public health pre-opening walk done and approved Attend Coordinate Public health inspector attends
Fire inspection done Schedule and host Fire inspector attends
Hood and fire-suppression tag visible and current Confirm
Punchlist closed out Walk and confirm Lead and resolve
Final cleaning complete Confirm Coordinate
Equipment commissioning complete (refrigeration, cookline, dishwasher) Confirm Lead
Soft-open trial nights scheduled Lead Be available for last fixes
Service contracts (hood cleaning, fire suppression, grease) lined up Lead with vendors Recommend reputable vendors
Signage live, storefront clean, opening day plan locked Lead Provide last-mile support Approve final signage if required

Buildup stays on call for the first week or two after opening for service and maintenance — small fixes, last-mile finishes, and quick adjustments after the kitchen has run real volume. The first weekend always teaches the operator something.


What experienced operators avoid

These are not "if you miss this you fail" warnings. They are the patterns experienced operators have learned to head off early. We see them across our project experience on Toronto and GTA restaurant fit-outs.


FAQ

How early should I bring a contractor in — before or after I sign the lease?

Before. A site walk with a contractor before signing usually takes one to two hours and surfaces panel, gas, exhaust, and structural constraints that would otherwise be locked in by the lease. It does not commit you to that contractor.

Who pulls the building permit — me, the architect, or the contractor?

The permit is normally pulled by the architect or designer of record, who has stamped the drawings. The contractor coordinates the construction-side documents and inspections that follow. The owner signs the application and pays the fees.

How long does a typical Toronto restaurant build-out take from lease signing to opening?

A typical Toronto restaurant tenant fit-out runs roughly four to seven months from lease signing to opening, with design taking about six to ten weeks, permit review six to twelve weeks, and construction eight to fourteen weeks. These overlap, but the dependencies above are real. Site complexity, landlord coordination, and equipment lead times can push the total. See our build-out timeline for how the calendar lays out.

Do I need a separate demo permit?

It depends on the municipality and the scope. Some cities issue demo as part of the building permit; others require a separate demo permit for any structural removal. Your contractor and architect will confirm during the permit submission phase.

Who is responsible if the landlord's electrical panel turns out to be undersized?

That depends on the work letter. If the work letter says the landlord delivers a panel of a certain capacity and they did not, it is a landlord obligation. If the work letter is silent, it usually becomes the tenant's cost. This is exactly why the work-letter line-by-line review in Phase 1 matters.

What inspections happen on opening week?

Typically the final building, electrical (ESA), gas (TSSA), plumbing, and fire inspections, followed by the public health pre-opening walk. The order matters — health and fire usually come last, after the trades inspections are signed off.

Does Buildup pull my permits for me?

Buildup is a construction-only contractor — permits are the architect's and engineer's stamped work. We coordinate the construction-side documents, schedule inspections, and run project management so the permit holder has clean information. For more on how this works, see our FAQ.

How do I use this checklist on a real project?

Print it. Bring it to your first site walk before signing the lease. Bring it to your first design meeting with the architect. Use it as the agenda for the weekly construction meeting. Mark items off as they close. The checklist is the artifact that keeps the four parallel projects (real estate, design, construction, regulatory) talking to each other.


Get the master checklist walked with you

If you are about to sign a lease, finalize design, or schedule final inspections and want a contractor to walk this checklist with you item by item, contact Buildup Contracting at info@buildupcontracting.ca or 647-477-7999. We attend site walks before lease signing across Toronto and the GTA at no cost to the operator.


Sources and references